May 24, 2026

Scheduled power service interruptions for January 2024

The Commonwealth Utilities Corp. would like to inform the general public that there will be scheduled power service interruptions for the month of January 2024, as CUC continues its ongoing system maintenance. See additional information below:

Wednesday, Jan. 10, 2024

Power Service Interruption Time: 8:30am-2:30pm

Area(s) Affected: San Antonio (Alu Dr. and Bula Ln.)

Water Wells Affected: None

Wastewater Facilities Affected: None

Traffic Light(s) Affected: None

Purpose: To allow the CUC linemen to replace four 45-feet concrete poles with 40-foot concrete poles.

Thursday, Jan. 11, 2024

Power Service Interruption Time: 8:30am-3:30pm

Area(s) Affected: CUC Lab and Water Division, Puerto Rico, and Sadog Tasi Treatment Plant

Water Wells Affected: PR-164

Wastewater Facilities Affected: Sadog Tasi Treatment Plant

Traffic Light(s) Affected: None

Momentary Power Service Interruption Time: 8:30am-9am and 3pm to 3:30pm

Area(s) Affected: Lower Base (CUC Power Plant-1 and DFW), CUC Lab and Water Division, Puerto Rico, Sadog Tasi Treatment Plant, and Lower Navy Hill

Water Wells Affected: PR-164

Wastewater Facilities Affected: S-1, S-3, and Sadog Tasi Treatment Plant

Traffic Light(s) Affected: Puerto Rico and Lower Navy HIll

Purpose: To allow the CUC linemen to replace four 45-foot wooden power poles with concrete poles.

Friday, Jan. 12, 2024

Power Service Interruption Time: 8:30am-2:30pm

Area(s) Affected: San Antonio (Guili St.)

Water Wells Affected: None

Wastewater Facilities Affected: None

Traffic Light(s) Affected: None

Purpose: To allow the CUC linemen to replace two 45-foot concrete poles with 40-foot concrete poles and replace a 45-foot wooden power pole with a 40-foot concrete pole.

Tuesday, Jan. 16, 2024

Power Service Interruption Time: 8:30am-3:30pm

Area(s) Affected: CUC Lab and Water Division, Puerto Rico, and Sadog Tasi Treatment Plant

Water Wells Affected: PR-164

Wastewater Facilities Affected: Sadog Tasi Treatment Plant

Traffic Light(s) Affected: None

Momentary Power Service Interruption Time: 8:30am-9am and 3pm-3:30pm

Area(s) Affected: Lower Base (CUC Power Plant-1 and DFW), CUC Lab and Water Division, Puerto Rico, Sadog Tasi Treatment Plant, and Lower Navy Hill

Water Well(s) Affected: PR-164

Wastewater Facilities Affected: S-1, S-3, and Sadog Tasi Treatment Plant

Traffic Light(s) Affected: Puerto Rico and Lower Navy Hill

Purpose: To allow the CUC linemen to replace four 45-foot wooden power poles with concrete poles.

Wednesday, Jan. 17, 2024

Power Service Interruption Time: 8:30am-2:30pm

Area(s) Affected: Afetnas (Palos Ln.)

Water Well(s) Affected: None

Wastewater Facilities Affected: None

Traffic Lights Affected: None

Purpose: To allow the CUC linemen to replace three 45-foot concrete poles with 40-foot concrete poles.

Thursday, Jan. 18, 2024

Power Service Interruption Time: 8:30am-2:30pm

Area(s) Affected: San Antonio

Water Well(s) Affected: None

Wastewater Facilities Affected: None

Traffic Light(s) Affected: None

Momentary Power Service Interruption Time: 8:30am-9am and 2pm-2:30pm

Area(s) Affected: San Antonio (Francisco M. Sablan Middle School and San Antonio Headstart)

Water Wells Affected: None

Wastewater Facilities Affected: None

Traffic Light(s) Affected: None

Purpose: To allow the CUC linemen to replace three 45-foot concrete poles with 40-foot concrete poles and replace two 45-foot wooden power poles with 40-foot concrete poles.

Tuesday, Jan. 23, 2024

Power Service Interruption Time: 8:30am-12:30pm

Area(s) Affected: Chalan Laulau (IT&E building) and Garapan (Fiesta barracks and former Nam Dae Moon Restaurant)

Water Wells Affected: None

Wastewater Facilities Affected: None

Traffic Light(s) Affected: None

Purpose: To allow the CUC linemen to replace two 40-foot wooden power poles with concrete poles and reinstall transformers, respectively.

Wednesday, Jan. 24, 2024

Power Service Interruption Time: 8:30am to 2:30pm

Area(s) Affected: Gualo Rai (BECQ building)

Water Wells Affected: None

Wastewater Facilities Affected: None

Traffic Light(s) Affected: None

Purpose: To allow the CUC linemen to replace a 40-foot wooden primary pole with a 40-foot concrete pole and reinstall a transformer.

Thursday, Jan 25, 2024

Power Service Interruption Time: 8:30am-2:30pm

Area(s) Affected: Northern Marianas College, Joeten Housing, and Fina Sisu

Water Well(s) Affected: NMC Water Tank/Reservoir, As Terlaje Booster Station and Chlorine Station

Wastewater Facilities Affected: W-8

Traffic Light(s) Affected: None

Purpose: To allow the CUC linemen to replace a 45-foot wooden power pole with a 40-foot concrete pole and reinstall a transformer.

Tuesday, Jan. 30, 2024

Power Service Interruption Time: 8:30am-12:30pm

Area(s) Affected: Chalan Kanoa (MS Villagomez building) and Garapan (Majesty Restaurant)

Water Wells) Affected: None

Wastewater Facilities Affected: None

Traffic Light(s) Affected: None

Purpose: To allow the CUC linemen to replace two 40-foot wooden power poles with concrete poles and reinstall transformers, respectively.

Wednesday, Jan. 31, 2024

Power Service Interruption Time: 8:30am-2:30pm

Area(s) Affected: Garapan (Saipan OneTel building, QQ Car Rental, High Roller Poker, and Sang Jee Car Rental)

Water Well(s) Affected: None

Wastewater Facilities Affected: None

Traffic Light(s) Affected: None

Purpose: To allow the CUC linemen to relocate and replace two 40-foot wooden power poles with 40-foot concrete poles, a 45-foot wooden power pole with a 40-foot concrete pole, and to reinstall transformers.

CUC continues to work diligently to minimize any inconvenience to its customers. For more information, contact its hotline at (670) 236-4333, visit its website, and monitor its Facebook page for the latest updates. For emergencies, contact Customer Service at (670) 664-4282. (CUC)

Map of the Commonwealth Utilities Corp.’s scheduled power service interruption on Jan. 11, 2024.

-CUC

Map of the Commonwealth Utilities Corp.’s scheduled power service interruption on Jan. 18, 2024.

-CUC

Map of the Commonwealth Utilities Corp.’s scheduled power service interruption on Jan. 23, 2024.

-CUC

Map of the Commonwealth Utilities Corp.’s scheduled power service interruption on Jan. 25, 2024.

-CUC

Map of the Commonwealth Utilities Corp.’s scheduled power service interruption on Jan. 30, 2024.

-CUC

Copyright © All rights reserved. | Newsphere by AF themes.