Editor’s Note: The following is CUC’s load shedding schedule for June 21 through 27, 2008.

8am – 10am Feeder-2: Second Partial
Beach Road Garapan at Kristo Rai Church south to San Jose Intersection

10am – 12pm Kiya-2: Second Partial
Portions of Koblerville, As Gonno, San Antonio and Afetnas

12pm – 2pm Feeder-4: Second Partial
Capitol Hill, Kagman and portions of Papago (Botanical Garden)

2pm – 4pm Feeder-1: Second & Third Partial
99 Cents Store and portions of Garapan and Upper Navy Hill
Feeder 3: Laterals
Upper Gualo Rai, Taro Sue, Ace Hardware, Rem Center, PTI, McDonald’s, XO Mart, H Mart

4pm – 6pm Feeder-7: Entire Grid
Lower Base industrial area, north to Tanapag, Achugao, San Roque, As Matuis and Marpi.

6pm – 8pm Kiya 1: Second Partial
CPA /Airport, Portions of Koblerville, As Perdido

8pm – 10pm Kiya-4: Second Partial

Mount Carmel and south to Portions of Chalan Kanoa

The first partial in each of the respective Feeder/Kiya could be included on the schedule should the second partial be insufficient. In addition, water and wastewater services will also be affected in the respective areas as a result of the power outages.

CUC will make all efforts to keep to this schedule. However, it may be modified in future public notices. Please be informed that such schedule may be altered to address particular emergencies when necessary. [B][I](CUC)[/I][/B]