CUC LOAD SHEDDING SCHEDULE

By
|
Posted on Jul 04 2008
Share

The Commonwealth Utilities Corp. said that, as the rehabilitation and maintenance repairs continue on the engines and generators at the Power Plant 1, the load shedding schedule for July 5 through July 11, 2008 will be as follows.

8am -10am Feeder-2: Entire Grid
CPA Puerto Rico (Sea Port) Garapan, Kristo Rai Church south to San JoseIntersection

10am – 12pm Kiya-1: Second Partial
CPA/Airport, As Perdido

12pm – 2pm Kiya-2: Second Partial
Koblerville, As Gonno, San Antonio and Afetnas

2pm – 4pm Feeder-1: Second & Third Partial
99 Cents Store and portions of Garapan and Upper Navy Hill, Annaks Condominiums

4pm – 6pm Feeder-7: Entire Grid
Lower Base industrial area, north to Tanapag, Achugao, San Roque, As Matuis and Marpi.

6pm – 8pm Kiya-4: Second Partial
Susupe, Mount Carmel south to portions of Chalan Kanoa and Chalan Kiya Village

8pm – 10pm Feeder-4: Second Partial
Capitol Hill, As Teo, Kagman and portions of Papago

The first partial in each of the respective feeder/kiya could be included in the schedule should the second partial be insufficient. In addition, water and wastewater services will also be affected in the respective areas as a result of the power outages. CUC will make all efforts to keep to this schedule; however, it may be modified in future public notices. Please be informed that such schedule may be altered to address particular emergencies when necessary. [B][I](CUC)[/I][/B]