The Commonwealth Utilities Corp. would like to inform the public that there will be scheduled power interruptions on the following dates, times and locations:
Monday, April 1, 2019, 8am to 4pm
• Outage type: Sectionalized feeder outage on the Feeder 4 distribution circuit
• Village location: Kagman 3
• Power service area(s) affected: Algeta Drive Kagman 2 and Kagman 3
• Water service area(s) affected: None
• Wastewater service area(s) affected: None
• Work to be performed: Replace six wooden poles with concrete ones
Monday, April 1, 2019, 8:30am to 1:30pm
• Outage type: Sectionalized feeder outage on the Kiya 1 distribution circuit
• Village location: Obyan
• Power service area(s) affected: None
• Water service area(s) affected: None
• Wastewater service area(s) affected: None
• Work to be performed: Replace four wooden poles with concrete ones
Tuesday, April 2, 2019, 8am to 4pm
• Outage type: Sectionalized feeder outage on the Kiya 1 distribution circuit
• Village location: Chalan Monsignor Guerrero, Dandan
• Power service area(s) affected: Chalan Monsignor Guerrero, Dandan
• Water service area(s) affected: None
• Wastewater service area(s) affected: None
• Work to be performed: Replace four wooden poles with concrete ones
Tuesday, April 2, 2019, 8:30am to 1:30pm
• Outage type: Sectionalized feeder outage on the Kiya 1 distribution circuit
• Village location: Obyan
• Power service area(s) affected: None
• Water service well(s) affected: None
• Wastewater service area(s) affected: None
• Work to be performed: Replace four (4) wooden poles with concrete ones
Wednesday, April 3, 2019, 8am to 4pm
• Outage type: Sectionalized feeder outage on the Kiya 1 distribution circuit
• Village location: Chalan Monsignor Guerrero, Dandan
• Power service area(s) affected: Chalan Monsignor Guerrero, Dandan
• Water service area(s) affected: None
• Wastewater service area(s) affected: A-13 and A-14
• Work to be performed: Replace four wooden poles with concrete ones
Wednesday, April 3, 2019, 8:30am to 1:30pm
• Outage type: Sectionalized feeder outage on the Kiya 1 distribution circuit
• Village location: Obyan
• Power service area(s) affected: None
• Water service area(s) affected: None
• Wastewater service area(s) affected: None
• Pole replacement(s): Replace four wooden poles with concrete ones
The purpose of the scheduled power interruptions is to de-energize utility lines and allow power line workers from CUC and its contracting company, Primary Source Electric, to safely replace 26 wooden poles with concrete ones. This is part of CUC’s ongoing effort to complete restoration work resulting from the system damage caused by Super Typhoon Yutu and CUC’s Water System Mitigation Project, which are both aimed at hardening and strengthening the power distribution system.
Because of the scale of work that will be performed, CUC asks travelers to take alternate routes or to exercise caution when driving through the working area.
For more information, contact the CUC Customer Call Center (664-4282) or monitor its Facebook page for the latest updates (https://www.facebook.com/CommonwealthUtilitiesCorporation/). (PR)