CUC revises scheduled power service interruptions for Jan.
The Commonwealth Utilities Corp. would like to inform the general public of a revised schedule for the power service interruptions. The original scheduled interruptions for Tuesday, Jan. 16, 2024, have been canceled until further notice, and Thursday, Jan. 25, 2023, has been rescheduled for Saturday, Jan. 20, 2024. See additional information below:
Friday, Jan. 12, 2024
Power Service Interruption Time: 8:30am-2:30pm
Area(s) Affected: San Antonio (Guili St.)
Water Wells Affected: None
Wastewater Facilities Affected: None
Traffic Light(s) Affected: None
Purpose: To allow the CUC linemen to replace two 45-foot concrete poles with 40-foot concrete poles and replace a 45-foot wooden power pole with a 40-foot concrete pole.
Wednesday, Jan. 17, 2024
Power Service Interruption Time: 8:30am-2:30pm
Area(s) Affected: Afetnas (Palos Ln.)
Water Wells Affected: None
Wastewater Facilities Affected: None
Traffic Light(s) Affected: None
Purpose: To allow the CUC linemen to replace three 45-foot concrete poles with 40-foot concrete poles.
Thursday, Jan. 18, 2024
Power Service Interruption Time: 8:30am-2:30pm
Area(s) Affected: San Antonio
Water Wells Affected: None
Wastewater Facilities Affected: None
Traffic Light(s) Affected: None
Momentary Power Service Interruption Time: 8:30am-9:00am and 2pm to 2:30pm
Area(s) Affected: San Antonio (Francisco M. Sablan Middle School and San Antonio Headstart)
Water Well(s) Affected: None
Wastewater Facilities Affected: None
Traffic Light(s) Affected: None
Purpose: To allow the CUC linemen to replace three 45-foot concrete poles with 40-foot concrete poles and replace two 45-foot wooden power poles with 40-foot concrete poles.
Saturday, Jan. 20, 2024
Power Service Interruption Time: 8:30am-2:30pm
Area(s) Affected: Northern Marianas College, Joeten Housing, and Fina Sisu
Water Wells Affected: NMC Water Tank/Reservoir, As Terlaje Booster Station and Chlorine Station
Wastewater Facilities Affected: W-8
Traffic Light(s) Affected: None
Purpose: To allow the CUC linemen to replace a 45-foot wooden power pole with a 40-foot concrete pole and reinstall a transformer.
Tuesday, Jan. 23, 2024
Power Service Interruption Time: 8:30am-12:30pm
Area(s) Affected: Chalan Laulau (IT&E building) and Garapan (Fiesta barracks and former Nam Dae Moon Restaurant)
Water Well(s) Affected: None
Wastewater Facilities Affected: None
Traffic Light(s) Affected: None
Purpose: To allow the CUC linemen to replace two 40-foot wooden power poles with concrete poles and reinstall transformers, respectively.
Wednesday, Jan. 24, 2024
Power Service Interruption Time: 8:30am-2:30pm
Area(s) Affected: Gualo Rai (BECQ building)
Water Wells Affected: None
Wastewater Facilities Affected: None
Traffic Light(s) Affected: None
Purpose: To allow the CUC linemen to replace a 40-foot wooden primary pole with a 40-foot concrete pole and reinstall a transformer.
Tuesday, Jan. 30, 2024
Power Service Interruption Time: 8:30am-12:30pm
Area(s) Affected: Chalan Kanoa (MS Villagomez building) and Garapan (Majesty Restaurant)
Water Wells Affected: None
Wastewater Facilities Affected: None
Traffic Light(s) Affected: None
Purpose: To allow the CUC linemen to replace two 40-foot wooden power poles with oncrete poles and reinstall transformers, respectively.
Wednesday, Jan. 31, 2024
Power Service Interruption Time: 8:30am-2:30pm
Area(s) Affected: Garapan Saipan OneTel building, QQ Car Rental, High Roller Poker, and Sang Jee Car Rental)
Water Well(s) Affected: None
Wastewater Facilities Affected: None
Traffic Lights Affected: None
Purpose: To allow the CUC linemen to relocate and replace two 40-foot wooden power poles with 40-foot concrete poles, a 45-foot wooden power pole with a 40-foot concrete pole, and to reinstall transformers.
CUC continues to work diligently to minimize any inconvenience to its customers. For more information, contact our hotline at (670) 236-4333, visit our website, and monitor our Facebook page for the latest updates. For emergencies, contact Customer Service at (670) 664-4282. (CUC)

CUC pix 1.jpg
CUC pix 2.jpg
CUC pix 3.jpg
CUC pix 4.jpg
CUC pix 5.jpg
CUC pix 6.jpg
CUC pix 7.jpg
Map of the Commonwealth Utilities Corp.’s scheduled power service interruption on Jan. 17, 2024.
-CUC

Map of the Commonwealth Utilities Corp.’s scheduled power service interruption on Jan. 18, 2024.
-CUC

Map of the Commonwealth Utilities Corp.’s scheduled power service interruption on Jan. 20, 2024.
-CUC

Map of the Commonwealth Utilities Corp.’s scheduled power service interruption on Jan. 23, 2024.
-CUC

Map of the Commonwealth Utilities Corp.’s scheduled power service interruption on Jan. 24, 2024.
-CUC

Map of the Commonwealth Utilities Corp.’s scheduled power service interruption on Jan. 30, 2024.
-CUC

Map of the Commonwealth Utilities Corp.’s scheduled power service interruption on Jan. 31, 2024.
-CUC